The Kunzvi–Harare pipeline project gained momentum in the past week, marked by the laying of the first three kilometres of pipeline about seven kilometres from the dam site. This milestone represents a major step toward easing Harare’s chronic water shortages, which have plagued the capital for over two decades.
The 48-kilometre pipeline will convey raw water from Kunzvi Dam to a treatment plant to be developed at Donnybrook in eastern Harare. Once complete, it will deliver up to 240 megalitres of water per day, significantly reducing the city’s water deficit. Currently, Harare receives about 400 megalitres daily against a demand of roughly 800 megalitres.
The pipeline forms a key part of the Harare East Water Augmentation Project, which had stalled for years mainly due to financial constraints. It is being implemented by local contractor Redan Bulk under a US$52 million tender awarded by the Zimbabwe National Water Authority (Zinwa).
Construction is expected to take two years, in line with the completion of Kunzvi Dam, which is scheduled to begin impounding water during the upcoming rainy season.
The project involves the installation of a 1.4-metre glass-reinforced polyester (GRP) pipeline and two booster pump stations. GRP pipes are lightweight, durable, and resistant to corrosion—qualities that reduce maintenance costs and extend the lifespan of infrastructure.
So far, about 30 workers have been employed, with the number expected to rise to 250 as construction progresses.
On-site, the contractor has deployed a high-tech mechanical trencher capable of excavating between 500 and 700 metres per day, depending on soil type, thus accelerating installation.
Last week, the first three kilometres of pipeline were laid about seven kilometres from the dam site.
Zinwa resident engineer Johanne Mwase said the project would not only augment Harare’s water supply but also deliver wider benefits.
“The Kunzvi–Harare pipeline is a raw water pipeline designed to supply Harare,” he said.
“It stretches 48 kilometres from Kunzvi Dam to Donnybrook Water Treatment Plant, with two booster stations along the way.
We are pleased that Redan Bulk, a local company, has demonstrated capacity to execute such a large infrastructure project using state-of-the-art equipment, including a powerful trencher capable of producing at least 500 metres a day.”
He added, “In fact, our other activities are struggling to keep up with the speed of excavation.”
Redan Bulk projects manager Engineer Lucio Chayeruka emphasized the importance of consistent funding to keep the project on schedule.
“Work is progressing well, and we aim to complete the pipeline construction in time for the commissioning of the Donnybrook Water Treatment Plant next year,” he said.
“The Kunzvi–Harare pipeline is a highly impactful social project. While our priority is to employ people from within Goromonzi District, we are also engaging workers from neighbouring districts, as this is a national project meant to be inclusive and responsive to broader social needs.”
He added that the team has invested heavily in state-of-the-art machinery and technology to ensure successful completion of the project.
“Excavation efficiency has been significantly enhanced through the use of the tracked trencher 1675 EVO,” said Mr. Chayeruka.
“This machine delivers high precision and produces well-graded spoil suitable for direct backfilling. Compared to conventional excavators, the 1675 EVO achieves trenching rates up to five times faster. Redan Bulk is the only company in Zimbabwe with such a trencher and among the few in Sub-Saharan Africa to possess this level of equipment.”
ALSO READ : Former Footballers Arrested for Drug Trafficking in Zimbabwe
He also revealed that digital systems are being introduced for recording installed utilities, with plans to establish a centralized control data centre for condition-based monitoring of the conveyance infrastructure.
“Zinwa has provided steady financial support, with Treasury aligning disbursements to project cash flow requirements through the Ministry of Finance,” he added.
Once completed, Kunzvi Dam will have a storage capacity of about 158 million cubic metres of water. This will support both domestic use and irrigation along the Harare–Goromonzi corridor, boosting agricultural productivity and rural development.
Construction of the dam officially began in 2021 and has made steady progress, with the dam wall nearing completion.