Calls for Audit as Trabablas Interchange Costs Jump by $26 Million

Finance and Economic Development Minister Mthuli Ncube came under intense scrutiny in Parliament this week after revelations that the Trabablas Interchange project had incurred an unexpected additional cost of US\$26 million.

During a heated session, Hon. Prosper Mutseyami directly questioned Minister Ncube on the supplementary expenditure, demanding a clear explanation of how such a substantial figure arose after the project’s budget had already been approved.

“Can you substantiate to the House as to how this supplementary US\$26 million would just come about when the budget had already been sorted, then we have extra figures to a situation of adding US\$26 million? How do you account for that, Hon. Minister?” asked Mutseyami.

Minister Ncube defended the expenditure, citing unforeseen structural modifications and rising material costs as key drivers of the additional funding requirement.

He argued that these adjustments were necessary to ensure the safety and long-term durability of the interchange, which is viewed as a flagship infrastructure project aimed at easing traffic congestion in the capital.

However, lawmakers across the aisle expressed skepticism over the explanation, accusing the Ministry of poor planning and lack of transparency.

Some MPs also raised concerns about potential mismanagement or misuse of public funds, calling for a full audit of the project’s finances.

The Trabablas Interchange, initially hailed as a major step toward modernizing Harare’s transport infrastructure, has now become a flashpoint in ongoing debates over government accountability and fiscal discipline.

Parliament is expected to summon further hearings to review detailed project documents and expenditure reports.

Meanwhile, public interest groups have urged the government to release all related contracts and procurement records to ensure transparency.

As the controversy unfolds, pressure is mounting on Minister Ncube to provide concrete evidence justifying the additional costs and to reassure both Parliament and the public that funds are being managed responsibly.

ALSO  READ : Harare School Director Arrested Over Alleged ZIMSEC Exam Fee Fraud

The Zimbabwe Times

Recent Posts

NetOne Dispels Rumors: CEO Mushanawani on Routine Annual Leave

Amidst a flurry of unsubstantiated social media speculation, an internal source at NetOne has definitively…

1 hour ago

Internal Push to Postpone Zanu-PF Leadership Vote Gains Momentum Ahead of Chinhoyi Conference

Zanu-PF is reportedly experiencing an internal push to cancel its scheduled 2027 elective congress, an…

17 hours ago

Blessful Catering (Pvt) Ltd Faces Court After NRZ Sting Uncovers Million-Litre Illicit Fuel Ring

A sophisticated, multi-million dollar fuel smuggling operation, allegedly orchestrated under the guise of a catering…

19 hours ago

Zimbabwe Empowers Municipal Police with Arrest, Investigation, and Prosecution Powers

In a significant move to bolster local governance and enhance compliance with council regulations, Zimbabwe's…

19 hours ago

Infant Emergency Ignored: Waterfalls Clinic Staff Accused of Turning Away Sick Babies Over Two Minutes

A shocking incident at the Waterfalls Satellite Clinic on Powell Road has ignited outrage, with…

21 hours ago

Victoria Falls Lights Up as iChange Nation Awards Celebrate a Decade of Transformational Leadership

Against the breathtaking backdrop of one of Africa’s most magnificent natural wonders, the prestigious iChange…

2 days ago